New Theatre and UCV System - Three Shires Hospital
Client
Circle Health Group
Location
Northampton
Duration
16 weeks
Value
£750,000
Working collaboratively with our supply chain, we successfully delivered the new theatre and UCV (Ultra Clean Ventilation) system whilst maintaining the live hospital environment for our client, Circle Health Group.
Project Profile
These works comprised major structural alterations and refurbishment in a live private sector hospital. The existing space required significant structural alterations to create the new operating facility. Temporary works were designed and installed to support the existing structure and roof, whilst beams were cut and carved and reinforced beams were formed in-situ to create the new space.
Upon completion of the structural alterations, we commenced the remaining works to create a modern operating theatre, including:
- MEP services
- Medical gases
- UPS and IPS systems
- Bender operating control panel with automated entrance doors
- Wall finishes
Challenge & Solution
As this was a live hospital with an adjacent theatre, we conducted all intrusive and potentially disruptive works out of hours. This was programmed in line with the theatre management team’s requirements.
See More Like This ....



New Theatre and UCV System - Three Shires Hospital
Client
Circle Health Group
Value
£750,000
Duration
16 weeks
Location
Northampton
Working collaboratively with our supply chain, we successfully delivered the new theatre and UCV (Ultra Clean Ventilation) system whilst maintaining the live hospital environment for our client, Circle Health Group.
Project Profile
These works comprised major structural alterations and refurbishment in a live private sector hospital.
The existing space required significant structural alterations to create the new operating facility. Temporary works were designed and installed to support the existing structure and roof, whilst beams were cut and carved and reinforced beams were formed in-situ to create the new space.
Upon completion of the structural alterations, we commenced the remaining works to create a modern operating theatre, including:
- MEP services
- Medical gases
- UPS and IPS systems
- Bender operating control panel with automated entrance doors
- Wall finishes



Challenge & Solution
As this was a live hospital with an adjacent theatre, we conducted all intrusive and potentially disruptive works out of hours. This was programmed in line with the theatre management team’s requirements.