Full Refurbishment - Old Hall Tavern Pub

Client

Star Pubs

Location

Chingford

Duration

4 weeks

Value

£180,000

Krypton undertook a full refurbishment of the Old Hall Tavern pub in Chingford within a four-week period to allow Star Pubs to open up to the public as soon as possible. 

Project Profile

The works involved removal of furniture and floor finishes before we undertook mechanical and electrical works and reinstalled the floor, wall and ceiling finishes. We also undertook a sympathetic restoration package to the bar joinery and cornicing within the building.

Whilst we were progressing with the internal fit out works, Krypton also undertook façade restoration works to prevent water ingress issues followed by decorations and LED lighting upgrades. 

Challenge & Solution

Prior to commencement onsite, we held meetings with the client  to review the scope and ensure early procurement orders were placed with key supply chain members, allowing us to fast track our programme to meet the client requirement. We also worked closely with the council to ensure our façade restoration works did not impact their highways. 

See More Like This ....

Full Refurbishment - Old Hall Tavern Pub

Client

Star Pubs

Value

£180,000

Duration

4 weeks

Location

Chingford

Krypton undertook a full refurbishment of the Old Hall Tavern pub in Chingford within a four-week period to allow Star Pubs to open up to the public as soon as possible.

Project Profile

The works involved removal of furniture and floor finishes before we undertook mechanical and electrical works and reinstalled the floor, wall and ceiling finishes. We also undertook a sympathetic restoration package to the bar joinery and cornicing within the building.

 

Whilst we were progressing with the internal fit out works, Krypton also undertook façade restoration works to prevent water ingress issues followed by decorations and LED lighting upgrades.

 

Challenge & Solution

Prior to commencement onsite, we held meetings with the client  to review the scope and ensure early procurement orders were placed with key supply chain members, allowing us to fast track our programme to meet the client requirement. We also worked closely with the council to ensure our façade restoration works did not impact their highways.

Enquire now

If you’re looking for more information, need to talk to someone about an enquiry or want to chat about your service needs, then you’ve come to the right place.

Please fill in our form and a member of our team will be in touch.