Full Refurbishment - Old Hall Tavern Pub
Client
Star Pubs
Location
Chingford
Duration
4 weeks
Value
£180,000
Krypton undertook a full refurbishment of the Old Hall Tavern pub in Chingford within a four-week period to allow Star Pubs to open up to the public as soon as possible.
Project Profile
The works involved removal of furniture and floor finishes before we undertook mechanical and electrical works and reinstalled the floor, wall and ceiling finishes. We also undertook a sympathetic restoration package to the bar joinery and cornicing within the building.
Whilst we were progressing with the internal fit out works, Krypton also undertook façade restoration works to prevent water ingress issues followed by decorations and LED lighting upgrades.
Challenge & Solution
Prior to commencement onsite, we held meetings with the client to review the scope and ensure early procurement orders were placed with key supply chain members, allowing us to fast track our programme to meet the client requirement. We also worked closely with the council to ensure our façade restoration works did not impact their highways.
See More Like This ....
Full Refurbishment - Old Hall Tavern Pub
Client
Star Pubs
Value
£180,000
Duration
4 weeks
Location
Chingford
Krypton undertook a full refurbishment of the Old Hall Tavern pub in Chingford within a four-week period to allow Star Pubs to open up to the public as soon as possible.
Project Profile
The works involved removal of furniture and floor finishes before we undertook mechanical and electrical works and reinstalled the floor, wall and ceiling finishes. We also undertook a sympathetic restoration package to the bar joinery and cornicing within the building.
Whilst we were progressing with the internal fit out works, Krypton also undertook façade restoration works to prevent water ingress issues followed by decorations and LED lighting upgrades.
Challenge & Solution
Prior to commencement onsite, we held meetings with the client to review the scope and ensure early procurement orders were placed with key supply chain members, allowing us to fast track our programme to meet the client requirement. We also worked closely with the council to ensure our façade restoration works did not impact their highways.